Follow

How does a new work contract affect work hour balance?

When a new work contract is created, flextime calculation is reset to zero so on the first day of the contract flextime shows 0 hours. If you want to transfer the users flextime, you need to adjust balance manually.

  1. Go to ToolsUser management
  2. Click to Edit an employee
  3. On the employee personal settings page, click to expand the Work hour adjustments section
  4. Click Add to enter a new adjustment
  5. Enter a positive or negative number to change the balance for the same date as the new contracts start date
  6. Save
Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

0 Comments

Powered by Zendesk